Jacques Dupont v Société Résidence
St. Clément
1997 MR 182
1997 SCJ 267
IN CHAMBERS
In the Supreme Court of Mauritius
In the matter of
Jacques Dupont
Applicant
v/s
Société Résidence St. Clément
Respondent
And in the presence of
The Municipal Council of Curepipe
Co-Respondent
Judgment
This is an application in Chambers to decide if whether
an injunction should be granted ordering the respondent
to stop forthwith the allegedly unlawful
construction of a six-storied building. No main case has been entered by
the applicant.
The point stressed in the affidavit in support of the application is that
the Development and Building Permit granted by the co-respondent is null
and void
without the obtention of an EIA (Environmental Impact Assessment) licence
and that the respondent, as a professional in the field of building construction,
should have sought for an EIA licence under S 18(4) of the Environment
Protection
Act 1991 (hereinafter referred to as the Act) before proceeding with such
a big project.
From the affidavits and documents produced, it is evident that the project
was originally designed to accommodate 16 apartments on 4 levels at St.
Clément
Street, Curepipe and that a Development and Building Permit for that
project was issued on 23 July 1991. As the building permit had to be
renewed, at
the request of the co-respondent, the respondent caused a fresh application
to
be made in 1996 for a development permit and for a building permit in
respect of the same site and the development project purported then to
house 24
apartments on six levels. A Development and Building Permit was consequently
issued
by the co-respondent. It is to be noted that according to the co-respondent,
an
EIA licence is not a prerequisite for the obtention of a Development
and Building Permit for purely residential purposes.
It would appear from the evidence available that had the initial project
been carried out, the applicant would have had no ground to complain,
especially after the respondent’s undertaking not to create any vues droites on
his adjoining premises in breach of article 678 of the Civil Code. However,
with the coming into force of a major part of the Act in November 1991, it
has become incumbent on a proponent who carries out any “undertaking”,
which word has been made to include “Major housing projects” as
listed in the schedule, to also obtain an EIA licence, irrespective of
any other licence, permit, or approval granted under any other enactment.
Failure
to comply with that requirement has been made an offence by S 13 (1)
of the Act.
The respondent, who is admittedly not the holder of an EIA licence, contends
that there is no duty on it to apply for such a licence as it is nowhere
specified that the six-storied construction it is undertaking falls within
the definition
of “Major housing projects”, thus necessitating an EIA licence.
It is submitted that the expression “Major housing projects” have
not been defined by the Act or by any regulations made thereunder. Another
relevant point raised by the respondent is that it had no obligation to apply
for an EIA licence as has been pointed out by the co-respondent, the more so,
it is submitted, since S 75(15) of the Act which purported to amend the Town
and Country Planning Act 1990 by making an EIA licence a prerequisite to the
obtention of a development permit in respect of an “undertaking” has
not yet been proclaimed, and is therefore not yet in force. It is advanced,
and quite pertinently in my view, that the respondent cannot be rebuked for
not complying with the law if the law maker does not specify what constitutes “Major
housing projects” which would have enjoined it to apply for an EIA licence.
The respondent has annexed four letters which were sent by its attorney to
the Ministry of Environment with a view to finding out whether there existed
any regulations made on the basis of the Act as amended and any classification
for the implementation of the First Schedule of the Act with respect to “Major
housing projects”. Finally, in February 1997, months after the construction
had been in progress, a reply was given to the respondent to the effect that
according to the policy of the EIA Committee, the construction of a building
of twenty or more flats is considered to be a “Major housing development” requiring
an EIA licence. The respondent contends that such a policy has no force of
law and does not bind the Court since it has not been made part of the law
by the Act or any regulation made thereunder. There is indeed substance in
that contention, especially when under S 2 of the Act the expression “environmental
laws” has been defined as meaning -
(a) (a) this Act and any regulations made under this Act, and includes
any direction, order, notice issued under, or any requirement imposed
by, this
Act;
(b) (b) any other enactment, or part of any other enactment which the Minister
may by regulations declare with the approval of the Commission
The contention upon which the applicant mainly relies is that the writ
ought to be granted in as much as the failure of the respondent to obtain
an EIA
licence constitutes a breach of the law for which there is a penal sanction.
He relies on the case of Poupard & Ors v. Harold & Ors [1909
MR 179] where it was held that a writ of injunction would be granted
when
the act
sought to be prohibited would, if committed, constitute a breach of a
penal law.
In that context I consider it relevant to refer to the case of Attorney-General
v. Chaudry & anor, 1971 1 WLR 1614 where the defendants had turned three
houses into an hotel and they took in residents. When the Greater London Council
became aware of it, they asked for the plans and found that there was a very
serious risk of fire. The defendants, who had previous experience in that connection
and knew fully well what the requirements were, were specifically warned by
the Greater London Council of the consequences if they persisted in using the
premises as an hotel without the necessary certificate which they were by law
required to obtain. They paid no heed to the admonition. The Council issued
a summons in the Magistrates’ Court alleging an offence under the law
but could get no early hearing. They joined in the Attorney-General to seek
an injunction in the High Court to restrain the defendants from permitting
the premises to be occupied without the required certificate. The Judge granted
an injunction to prevent the occupation of the hotel premises until the safety
precautions would have been taken. The Court of Appeal maintained the trial
Judge’s decision.
In that case Lord Denning M.R. said the following at p. 1624:
Whenever Parliament has enacted a law and given a particular remedy for
the breach of it, such remedy being in an inferior court, nevertheless
the High
Court always has reserve power to enforce the law so enacted by way of
an injunction or declaration or other suitable remedy. The High Court has
jurisdiction to
ensure obedience to the law whenever it is just and convenient so to do.
The question for decision is whether in the circumstances existing in the
present case I should use my discretion to grant an injunction ordering
the respondent
to stop its construction altogether.
It is obvious that the main concern of the applicant is that for reasons
known to himself, he does not want to see materialize such a housing
project near
his house. There is no affidavit evidence before me giving the stand
of the Ministry of Environment as the applicant has not thought fit to
put
them
into cause. It is not to be overlooked that the Ministry might after
all have granted
an EIA licence for a project at the site in question, had such a licence
been applied for. Another aspect to be taken into consideration is that
according to the applicant himself, as averred in his first affidavit,
the construction
started in April or May 1996. It would appear therefore that he allowed
the construction to proceed for months before seizing the Judge in Chambers
for
an injunction. It is to be noted that the respondent, even after having
obtained the Development and Building Permit from the co-respondent,
and even when
believing
that there was no obligation on it to apply for an EIA licence, has nevertheless
contacted the Ministry of Environment to ascertain whether any regulations
have been made or whether what constitutes “Major housing projects” has
been specified by the law. The respondent has explained why it does not
consider itself to be bound by the letter which it finally managed to
obtain from
the Ministry. As regards the contention of the applicant to the effect
that the
Development and Building Permit granted by the co-respondent is null
and void in the absence of an EIA licence, it is clear that such is not
the
case since
S 75(15) of the Act is not in force yet.
The other point that requires attention is whether the applicant has
committed an act in breach of S 13(1) of the Act. The state of the legislation
regarding
the implementation of the Act, especially as far as the application for
an EIA licence is concerned, cannot be said to be unambiguous. “Major housing
projects” is not defined by the Act nor by any regulations made thereunder.
That expression appears together with the other undertakings specified under
the heading Urban Development Projects in the schedule, like “Hospital
construction”, “Restructuring of land holdings an urban fringes”, “Industrial
estate”, “Depot for buses and motor vehicles”, “Traffic
centre”, “New town and satellite town Hotels and motels”.
I agree with the submission of learned Counsel for the respondent that
the expression “Major housing projects” has to be defined
and made known to the public either by way of regulations or general
notice
published
in the Government Gazette. Since a citizen cannot plead ignorance of
the law, he and his rights and investment cannot be subjected to policy
which
is liable
to be changed, sometimes whimsically and capriciously, and which has
not been translated into law. It is not to be forgotten that the Court
is concerned
with the interpretation of the law.
After thoughtful consideration, I have reached the conclusion that it
has not been established to my satisfaction from the affidavits placed
before
me that
the applicant is proceeding with an “undertaking” without
the required certificate in breach of the Act. In all the circumstances
of
the case as elaborated
above, I consider that it would not be just and convenient for me to
issue an injunction in this matter. I am further of the view that the
balance
of convenience dictates that I should exercise my discretion in not granting
the injunction. I therefore set aside the application with costs.
S. Peeroo
Judge
|